Quiz

  1. 1
    Advanced

    What are the three project cost reference values that are used by earned value analysis?

  2. 2
    Advanced

    In earned value analysis, what is the relationship between Current PV and Cumulative PV?

  3. 3
    Advanced

    What is a variance on a project?

  4. 4
    Advanced

    When calculating cost variance on a project while it is partially complete, what is a factor that project managers must account for when comparing the actual costs to the planned or budgeted costs?

  5. 5
    Advanced

    What is the difference between a positive and negative schedule variance?

  6. 6
    Advanced

    Under what circumstances will the EV for the task exceed the PV for the task?

  7. 7
    Advanced

    What does it mean to set the EV for a task using the 30 - 70 rule?