GoSkills
Help Sign up Share
Back to course

Add Lag and Review the Critical Path

Compact player layout Large player layout

Locked lesson.

Upgrade

  • Lesson resourcesResources
  • Quick referenceReference
  • Transcript
  • Notes

About this lesson

When you are updating tasks in a project, you might want to make some light adjustments. You can use the free slack field to see how much time you have before the task becomes critical.

Lesson versions

Multiple versions of this lesson are available, choose the appropriate version for you:

2013, 2019/365.

Exercise files

Download this lesson’s related exercise files.

Add Lag and Review the Critical Path.mpp.mpp
355.5 KB
Add Lag and Review the Critical Path - Completed.mpp.mpp
356 KB

Quick reference

Add Lag and Review the Critical Path

As mentioned in previous lessons, any task in the critical path can directly affect the finish date for your project. Just add one extra day of duration to a critical task and you push the project out a day. Subtract a day from a critical task and you pull the project in one day.

You can use the free slack field to see how much time you have before the task becomes critical.

When you are updating tasks in a project, you might want to make some light adjustments. You should always be aware of when you are updating critical tasks or non-critical tasks.

Further Discussion

When you are updating your project, you might find tasks that should not happen immediately after another. In the video lesson, you have to move a task out so people are not walking all over wet cement. You could simply add a task in the project to represent the extra time, but that is one more task in the project. Instead, you can add lag to the task.

Lag allows you to adjust the time it takes between when one task starts and the other one finishes. You can also use negative lag to force a task to start before another one finishes.

Steps

Follow these steps to use lag in your project:

  • Double-click a task that can start earlier or later than the predecessor relationship currently allows.
  • The task information dialog appears. Click the predecessors tab.
  • Type a lag (positive or negative).
  • While still in the task information dialog, click the Notes tab and enter the reason for why you are using this relationship.
  • Click the OK button.
Login to download
  • 00:04 You've done a lot of work so far to create a Microsoft project schedule.
  • 00:08 However, one of the things that we have not done yet
  • 00:11 is to really look at how we can optimise the plan.
  • 00:15 This is something you always want to to go back and do with your team.
  • 00:18 So for example, after your team has suggested the tasks,
  • 00:22 the durations, the linkages with the predecessors successors.
  • 00:26 And we've taken a look at the resource assignments.
  • 00:30 We want to step back and say, did we miss anything?
  • 00:33 Can we make the project come in a little bit earlier?
  • 00:36 Or are there things that we forgot that's going to push the project out?
  • 00:40 So I'm going to talk a little bit about using the critical path and
  • 00:45 making some adjustments to your schedule so
  • 00:48 that you have a better picture as to when the project will be complete.
  • 00:53 When we make changes to our project,
  • 00:56 we want to keep an eye on any task that's critical.
  • 00:59 Now remember that critical tasks mean that if you change by even
  • 01:04 one day you'll change the entire duration of the project.
  • 01:08 Let me show you what that means.
  • 01:10 First, make sure you're in a Gantt chart view.
  • 01:13 Then click the Gantt Chart Tools, Contextual Format tab.
  • 01:17 In the bar style section, you'll find a critical tasks check box.
  • 01:22 Just go ahead and select that.
  • 01:24 So when you select this, you'll see that the bars and the Gantt chart turn red.
  • 01:30 I can also insert a column to the right of task name.
  • 01:34 So if I right click test name and choose Insert column.
  • 01:38 I'll type critical and press Enter.
  • 01:41 Now you can see there are certain tasks that are critical and
  • 01:44 certain tasksthat are not.
  • 01:45 Watch what happens when I change acquire land from 30 days to 31 days.
  • 01:51 Watch the full duration of the project.
  • 01:53 Right now it's at 207 days.
  • 01:56 So we'll change acquire land to 31 and
  • 01:59 now the duration of the project is 208, I'll change this to 29.
  • 02:04 And you can see the duration of the project is 206.
  • 02:08 I'll set this back to 30 days.
  • 02:11 So that's how we can see the impact of changing critical path tasks.
  • 02:17 So far I've spent a lot of time talking about critical path tasks and
  • 02:21 how important they are, but what if a task is not in the critical path?
  • 02:24 Let's just scroll down a little bit here.
  • 02:27 And let's take a look at these blue tasks over here.
  • 02:30 I'm going to zoom in a little bit.
  • 02:32 So I'll move things around and zoom in.
  • 02:36 It's a little bit too much.
  • 02:38 There we go.
  • 02:39 So we have these tasks here that clearly have some time in between.
  • 02:43 So if I click the Format tab again, the Gantt Chart Tools Format tab,
  • 02:48 and click the Slack checkbox.
  • 02:50 You'll see how the Gantt chart is showing this little line underneath some of
  • 02:55 these tasks.
  • 02:56 Well this line is representing how much time you have before the task falls
  • 03:00 into the critical path.
  • 03:02 I can also insert a column for this.
  • 03:05 So if I right click on task name and choose Insert Column.
  • 03:10 I can type free Slack and press Enter.
  • 03:16 Now what I can do is take a look at this task, hire interior designer.
  • 03:20 It says there's 38 days of free Slack, which means 38 days
  • 03:25 plus 5 days is what would make this task fall into the critical path.
  • 03:30 So if I type 43 and press Enter, you can see it goes into the critical path.
  • 03:36 If I type 42 or anything less, it will not.
  • 03:40 So if I need to spend more time finding and
  • 03:43 hiring a interior designer, then I actually have time to do that.
  • 03:48 I'll press Undo a few times to get this back.
  • 03:51 So that's just a quick little overview of how we look at critical tasks and Slack.
  • 03:56 The next thing we're going to do is make a few minor adjustments to our tasks.
  • 04:01 Now as I talk to my team,
  • 04:03 I find out that there's two tasks that we need to make some adjustments to.
  • 04:07 The first is task number 11, install house frame.
  • 04:11 My team member rightly points out that we can't be walking around in wet cement.
  • 04:15 We have to install the house frame after it's dried.
  • 04:17 So I'm going to double click on Install house frame and
  • 04:21 go to predecessors and create a lag of 5 days and click OK.
  • 04:26 What this does, is it pushes out the task five days for us.
  • 04:31 I could have inserted another task that said wait for foundation to dry, but
  • 04:35 that would just be some new tasks that I need to manage.
  • 04:39 Or I could have had entered a date but remember,
  • 04:41 we do not want to ever have to enter a start date.
  • 04:44 So this works out really well for us.
  • 04:46 Now it says 10 linked to task 10 finished to start plus 5 days.
  • 04:54 We'll add a note and this note will help us remember why we did this,
  • 05:01 added 5 days positive lag to wait for foundation to dry.
  • 05:08 We can do that one more time, but in the opposite direction.
  • 05:12 So here's task 25, add furniture.
  • 05:15 One of my team members points out that we don't have
  • 05:19 to wait exactly until this build out kitchen task is done.
  • 05:23 So I double click, choose Predecessors and
  • 05:26 set the lag to -6 days for this build out of the kitchen.
  • 05:31 And what we've done is we've pulled the task in to
  • 05:35 actually finish a little bit earlier.
  • 05:38 In total we've brought the entire project down by one day.
  • 05:42 It was at 207 days now it's at 206.
  • 05:46 So we push one task out 5 days, but we brought another task in 6 days.

Lesson notes are only available for subscribers.

Add Milestones to the Project
5m:31s
Adjust Resource Allocations
5m:02s

PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.

Share this lesson and earn rewards

Facebook Twitter LinkedIn WhatsApp Email

Gift this course
Give feedback

How is your GoSkills experience?

I need help

Your feedback has been sent

Thank you

Back to the top

© 2021 GoSkills Ltd. Skills for career advancement