Resource allocations display as a red person icon in the indicators column. This column displays in most Gantt chart views. In nearly any task-level view, you can insert the indicators column if you need to.

Lesson versions

Multiple versions of this lesson are available, choose the appropriate version for you:

2013, 2019/365.

Exercise files

Download this lesson’s related exercise files.

Adjust Resource Allocations.mpp.mpp
362.5 KB
Adjust Resource Allocations - Completed.mpp.mpp
362.5 KB

Quick reference

Adjust Resource Allocations

Resource allocations display as a red person icon in the indicators column. This column displays in most Gantt chart views. In nearly any task-level view, you can insert the indicators column if you need to.

Further Discussion

Microsoft Project offers a resource leveling feature however I recommend you avoid using it.

Steps

To identify resource over allocations your project, follow these steps.

  • Click the View tab and click the details checkbox.
  • In the picklist next to the details checkbox, select the Resource Graph item.
Login to download
  • 00:04 So far, you have done a lot to set up your project schedule.
  • 00:07 And for all intents and purposes, you're ready to go.
  • 00:11 You can always make changes as you need to.
  • 00:14 However, there is an important warning that we should be looking at.
  • 00:18 And it looks like we have some over allocated resources.
  • 00:21 These are represented by these red person icons in the indicator column.
  • 00:27 I'm going to show you how to address resource over allocations in this lesson.
  • 00:33 One way to address an over allocated resource is to let Microsoft Project
  • 00:38 handle this for you.
  • 00:39 So you can see here I have this, right click for options menu item,
  • 00:45 and I can just choose Reschedule to Available Date.
  • 00:49 And as I do this to resources, usually working from the bottom up,
  • 00:55 you can see project is rescheduling.
  • 00:58 And it's fixed those over allocations, the red people are gone.
  • 01:02 But let's look over here at what it did to our project.
  • 01:06 What it did is it said, well, here's this generic resource called general
  • 01:11 contractor that was over allocated, and so it moved my tasks around.
  • 01:16 Notice now, that my start to start relationship that I created on
  • 01:20 these tasks, it's no longer being recognized.
  • 01:24 Other tasks are moved out and I'm not saying this nice
  • 01:28 waterfall style approach to completing our project.
  • 01:33 So, I do not recommend that you allow Microsoft Project to
  • 01:37 automatically reschedule your project.
  • 01:41 So I'm going to go ahead and undo all those changes so
  • 01:45 that it goes back to where the project was when I first opened it.
  • 01:50 Just so you're aware, there is a Resource tab and a Level all button.
  • 01:55 If you click that, it does the same exact thing as right clicking and
  • 02:00 asking project to reschedule.
  • 02:02 So I'm going to click the Undo button or
  • 02:05 press Ctrl+Z to go back to our original schedule.
  • 02:10 We do not want Microsoft Project to reschedule resources for
  • 02:13 us unless it makes absolute sense and
  • 02:16 exactly what's going to happen in your project when you do that.
  • 02:20 So what is the right method for leveling your project?
  • 02:26 There's no hard and fast rule, but I'm going to show you a method that works for
  • 02:31 most people.
  • 02:31 Click the View tab and click the Details checkbox.
  • 02:36 If we call this brings up the split view.
  • 02:40 Now on the drop down pick list next to the check box,
  • 02:44 go ahead and chose Resource graph.
  • 02:46 Now what you can see is a graph showing were we have e
  • 02:51 resource allocations and over allocations.
  • 02:55 I would to scroll down in the gaunt chart and
  • 02:59 go to some of the resources that are showing over allocations.
  • 03:04 Now, here's how I would handle this.
  • 03:06 I would sit down with the general contractor and
  • 03:10 say it looks like we're over allocated.
  • 03:13 Is this going to be a problem or not?
  • 03:15 And the general contractor might say, generally speaking,
  • 03:19 I can provide you all the resources that you need.
  • 03:23 However, with this install cabling and install HVAC,
  • 03:28 it might be some of the same people.
  • 03:30 So how about we change the linkage here a little bit, and
  • 03:35 instead of linking to task 11, could you link it to task 12.
  • 03:40 This way, after the people that are doing the cabling
  • 03:44 installation can then work with the HVAC people.
  • 03:48 Now that we've done that you can see the over allocation has been reduced.
  • 03:51 And the general contractor is telling us that these read over
  • 03:55 allocations are okay because they have the resources to handle the work.
  • 04:00 Given this is a fundamentals course,
  • 04:02 I recommend you use this approach that I just taught you, for leveling resources.
  • 04:07 As you become more advanced and working with Microsoft projects,
  • 04:10 you'll find your own methods.
  • 04:11 And there's certainly many methods that are listed online that you can look at on
  • 04:16 YouTube or on Google.
  • 04:17 Now, up here at the top of the page with the View menu is still selected,
  • 04:22 we want to get rid of this resource graph when we don't need it.
  • 04:26 So we just deselect Details.
  • 04:28 Now something that you might notice when you click Details is that it goes
  • 04:33 back to your standard split view.
  • 04:35 So remember when you want to see the resource graph, you have to
  • 04:39 choose the pick list and choose Resource Graph and you'll get that back.
  • 04:43 I'm going to deselect Details,
  • 04:45 as we're going to set a baseline in our next lesson.

Lesson notes are only available for subscribers.

Add Lag and Review the Critical Path
06m:03s
Create a Baseline
05m:33s

PMI, PMP, CAPM and PMBOK are registered marks of the Project Management Institute, Inc.

Share this lesson and earn rewards

Facebook Twitter LinkedIn WhatsApp Email

Gift this course
Give feedback

How is your GoSkills experience?

I need help

Your feedback has been sent

Thank you

Back to the top

© 2023 GoSkills Ltd. Skills for career advancement